Project Description:
BARNSTABLE- SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 28 @ 3 LOCATIONS: LUMBERT MILLS ROAD, SOUTH COUNTY ROAD AND ROUTE 149
This project involves the installation of new traffic signal systems at 3 locations on Route 28 and associated geometric improvements.
Location:
  • Town of Barnstable
  • Construction Begins: Autumn 2009
    Construction Ends: Spring 2011
    Resident Engineer: Joseph Gedraitis
    Construction Contract Value: $2,436,896.00
    Construction Bid Price: $1,981,360.25
    Initial Construction Estimate: $2,307,305.00
    MassHighway District: District 5

    Contracts (2) Progress
    # 34455 -- Design -- Traffic Signing/Signals
    Statewide - design of intersection improvement projects, modifications of existing state highway traffic signal locations and the upgrade of the Statewide Highway Lighting Sys Final
    # 59674 -- Construction Contract
    Intersection Improvements and Related Work on Route 28 (Falmouth Road) at 3 Locations.

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/06/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/10/2003
    Project Review Committee Received 11/10/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/09/2004
    Project Status Initiated 09/23/2005
    Project Status Advertised 06/27/2009
    Prj Scope & Negotiation
    Consultant Contract Process NTP Issued 09/14/2005
    Design
    Highway Design Process 25% Plans Received 05/12/2008
    Highway Design Process Meeting Request 01/07/2008
    Highway Design Process 25% Comments to DE 06/20/2008
    Highway Design Process Design Public Hearing 08/13/2008
    75% Design 75% Plans Received 11/25/2008
    75% Design 75% Comments to DE 01/22/2009
    100% Design 100% Plans Received 03/31/2009
    100% Design 100% Comments to DE 05/14/2009
    Final Design PS&E to CEPO 06/24/2009
    Final Design PS&E Received 06/15/2009
    Right of Way
    Certification Issued 06/10/2009
    Plans Accepted 02/25/2009
    Requirements Requirements 12/04/2008
    Advanced Title Exam Requested 02/25/2009
    Advanced Title Exam Completed 04/15/2009
    Registry Plans/Instruments Requested 03/31/2009
    Registry Plans/Instruments Received 04/17/2009
    Registry Plans/Instruments Accepted 04/28/2009
    Traffic
    25% Design Review 25% Plans Received 05/13/2008
    25% Design Review 25% Plans Approved 06/23/2008
    75% Traffic Plans 75% Plans Received 11/26/2008
    75% Traffic Plans 75% Plans Approved 01/27/2009
    100% Traffic Plans 100% Plans Received 04/01/2009
    100% Traffic Plans 100% Plans Approved 04/24/2009
    Design Exceptions
    Environmental
    Wetlands Protection Act Permit Issued 03/04/2009
    Wetlands Protection Act Permit Expires 03/04/2012
    ITS
    Utilities
    Non Participating