Project Description:
DEERFIELD- MONTAGUE- BIKE TRAIL CONSTRUCTION, FRANKLIN COUNTY BIKEWAY (PHASE I, Part A)
This proposed project was originally a part of Project # 602958 Franklin County Bikeway (Phase 1, Part B) in Montague that was advertised August 23, 2003. This phase of the bikeway project begins at McClelland Farm Road and continues north along existing abandoned railroad right-of-way before terminating at Montague City Road for a distance of approximately 1.3 miles. The project also includes the modification of the three span, wood trestle, former railroad bridge over the Connecticut River into a bikeway bridge.
Location:
  • Town of Montague
  • Construction Begins: Winter 2005/2006
    Construction Ends: Spring 2008
    Resident Engineer: Daniel Boucher
    Construction Contract Value: $2,024,547.82
    Construction Bid Price: $1,616,692.50
    Initial Construction Estimate: $1,164,690.00
    MassHighway District: District 2
    Current Status: Bike path under construction (as of 04/10/2006)
    Additional Info: Project suspended for winter (as of 12/05/2007)

    Contracts (1) Progress
    # 43206 -- Construction Contract
    PF# 604128 - DEERFIELD- MONTAGUE- BIKE TRAIL CONSTRUCTION, FRANKLIN COUNTY BIKEWAY (PHASE I, Part A) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/24/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bike path under construction
    Additional Info
    Project suspended for winter
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/2003
    Project Review Committee Received 12/01/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 12/30/2003
    Project Status Advertised 09/25/2004
    Prj Scope & Negotiation
    Design
    25% Design 25% Plans Received 04/16/1999
    25% Design 25% Comments to DE 11/10/1999
    25% Design Design Public Hearing 06/15/2000
    Distribution of Plans 75% Plans Received 07/01/2001
    Distribution of Plans 75% Comments to DE 10/30/2001
    100% Design 100% Plans Received 05/27/2004
    100% Design 100% Plans Received 06/25/2004
    Geotechnical PS&E to FAPO 09/20/2004
    Geotechnical PS&E Received 11/11/2004
    Right of Way
    Traffic
    100% Design Review 100% Plans Received 06/03/2004
    100% Traffic Plans 100% Plans Approved 06/29/2004
    100% TCA 100% Plans Approved 06/08/2004
    Design Exceptions
    Environmental
    Document/Plan Submissions 0 06/29/2004
    ITS
    Utilities
    Non Participating