| Project Description: |
NEWTON- RESURFACING & RELATED WORK ON ROUTE 9 (BOYLSTON STREET) FROM THE WELLESLEY/NEWTON C.L. TO NEWTON/BROOKLINE C.L.
This resurfacing project work will include updates to the guardrail and improvements to the existing drainage structures.
|
| Location: |
|
| Construction Begins: | Spring 2009 |
| Construction Ends: | Spring 2011 |
| Resident Engineer: | Jekishan Patel![]() |
| Construction Contract Value: | $4,476,144.00 |
| Construction Bid Price: | $3,847,995.20 |
| Initial Construction Estimate: | $3,930,172.00 |
| MassHighway District: | District 4 |
| Current Status: | The contractor is currently in shutdown due to utility related issues. (as of 07/27/2010) |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||