NEWTON- REHABILITATION OF NEEDHAM STREET, FROM NEEDHAM T.L. TO WINCHESTER STREET & FROM NEEDHAM STREET TO ROUTE 9
The roadway will be rehabilitated and widened to accommodate bicycles. The project includes new sidewalks, reconfigured intersections and revised traffic signals. Following the rehabilitation the roadway will be under the jurisdiction of the City of Newton.
Location:
  • City of Newton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2013
    Project Manager: Robert Kimungu
    Estimated Construction Cost: $6,000,000.00
    MassHighway District: District 4
    Current Status: Design Exception Approved. (as of 08/31/2007)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 11/08/2004
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 03/16/2006
    Right of Way
    Plans Requested 04/03/2006
    Plans Received 06/19/2006
    Requirements Requirements 04/03/2006
    Traffic
    25% Design Review 25% Plans Received 03/31/2006
    25% Design Review Plans Resubmitted 08/17/2006
    Design Exceptions
    Regular Design Exception Approved 08/31/2007
    Regular Design Exception Submitted 03/16/2006
    Environmental
    ITS
    Utilities