DEDHAM- NEEDHAM- WELLESLEY- WESTWOOD- RESURFACING AND RELATED WORK, I-95
Location:
  • Town of Dedham
  • Town of Needham
  • Town of Wellesley
  • Town of Westwood
  • Construction Begins: Winter 2005/2006
    Construction Ends: Winter 2006/2007
    Resident Engineer: Robert Blackmar
    Construction Contract Value: $4,128,504.00
    Construction Bid Price: $3,517,004.06
    Initial Construction Estimate: $3,288,886.00
    MassHighway District: District 4
    Current Status: All roadway work and related items completed. Final inspection of traffic collection data stations forthcoming. (as of 11/09/2007)

    Contracts (1) Progress
    # 43092 -- Construction Contract
    The work shall consist of resurfacing a segment of Interstate 95 in Dedham, Westwood, and Needham and related work. 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/12/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All roadway work and related items completed. Final inspection of traffic collection data stations forthcoming.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 12/10/2004
    Project Status Advertised 06/25/2005
    Prj Scope & Negotiation
    Design
    100% Design 100% Plans Complete 06/01/2005
    Final Design PS&E to CEPO 06/21/2005
    Final Design PS&E Received 06/01/2005
    Final Design PS&E Received 06/21/2005
    Right of Way
    Requirements Requirements 05/10/2005
    Traffic
    75% TMP 75% Plans Approved 05/04/2005
    100% Design Review 100% Plans Received 06/08/2005
    100% Design Review 100% Plans Approved 07/12/2005
    100% TMP 100% Plans Received 06/08/2005
    100% TMP 100% Plans Approved 07/12/2005
    Design Exceptions
    Environmental
    ITS
    Utilities