BOSTON- CONSTRUCTION OF TYPE II NOISE BARRIER , I-93 (SOUTHEAST EXPRESSWAY) AT SAVIN HILL AVENUE
Location:
  • City of Boston
  • Construction Begins: Winter 2005/2006
    Construction Ends: Autumn 2007
    Resident Engineer: Girard Allien
    Construction Contract Value: $774,251.00
    Construction Bid Price: $563,410.00
    Initial Construction Estimate: $313,900.00
    MassHighway District: District 4
    Current Status: This project is complete. Final inspection was held on 8/27/07. (as of 09/06/2007)

    Contracts (1) Progress
    # 43446 -- Construction Contract
    Sound Barrier along I-93 at savin Hill Avenue in Boston 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/09/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is complete. Final inspection was held on 8/27/07.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 03/05/2005
    Project Status Advertised 07/23/2005
    Prj Scope & Negotiation
    Design
    100% Design 100% Plans Received 06/08/2005
    Final Design PS&E to CEPO 07/21/2005
    Final Design PS&E Received 07/21/2005
    Right of Way
    Certification Issued 04/19/2005
    Traffic
    100% TMP 100% Plans Received 03/16/2005
    100% TMP 100% Plans Approved 03/31/2005
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating