Project Description:
NEWTON- WELLESLEY- WESTON- INTERSTATE MAINTENANCE ON I-95
Location:
  • City of Newton
  • Town of Wellesley
  • Town of Weston
  • Construction Begins: Spring 2008
    Construction Ends: Autumn 2010
    Resident Engineer: Paul Pascucci
    Construction Contract Value: $21,695,321.80
    Construction Bid Price: $18,087,602.82
    Initial Construction Estimate: $15,915,991.50
    MassHighway District: District 4
    Current Status: The Contractor will continue noise barrier work through the spring and summer of 2010. Night paving has resumed. (as of 07/23/2010)

    Contracts (1) Progress
    # 54039 -- Construction Contract
    Work consists of safety and maintenance improvements along Route I-95 in Wellesley, Newton and Weston. 92% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/28/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The Contractor will continue noise barrier work through the spring and summer of 2010. Night paving has resumed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 09/27/2005
    Project Status Advertised 09/23/2006
    Project Status Advertised 01/12/2008
    Prj Scope & Negotiation
    Design
    75% Design 75% Plans Received 06/29/2006
    Final Design PS&E to CEPO 11/15/2007
    Final Design PS&E Received 11/14/2007
    Right of Way
    Requirements Requirements 10/21/2005
    Traffic
    100% Design Review 100% Plans Received 01/26/2006
    100% Design Review 100% Plans Approved 03/01/2006
    100% TMP 100% Plans Received 01/26/2006
    100% TMP 100% Plans Approved 03/01/2006
    Design Exceptions
    Environmental
    Section Cleared 25% Plans Received 12/13/2005
    ITS
    Utilities
    Non Participating