| Project Description: |
QUINCY- CENTER CONCOURSE IMPROVEMENTS ON REVERE ROAD (MCGRATH HIGHWAY - PHASE II)
This 1900-foot project includes roadway and sidewalk reconstruction and new traffic signals along the new alignment from the end of the Highway Division's Phase I project to the project limit west of the Washington Street intersection. A 600 ft section of Quincy Avenue/Hancock Street is proposed for reconstruction including the intersection with Elm Street/School Street. The project continues along Elm Street improving the roadway layout and corner geometries. Construction advances onto Mechanic Street for 500 feet concluding at the intersection with Revere Road.
|
| Location: |
|
| Construction Begins: | Winter 2009/2010 |
| Construction Ends: | Spring 2012 |
| Resident Engineer: | Prasun (P.K.) Sen![]() |
| Construction Contract Value: | $4,703,883.00 |
| Construction Bid Price: | $5,075,947.37 |
| Initial Construction Estimate: | $7,543,847.30 |
| Funding Provision: | This project is planned to be funded through the 2010 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
| MassHighway District: | District 4 |
|
Bridges |
||||||||
|
||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||