DEDHAM- BRIDGE REPLACEMENT, D-05-033, PROVIDENCE HIGHWAY OVER MOTHER BROOK
This bridge project involves the complete replacement of the Providence Highway Bridge over Mother Brook (Bridge No. D-05-033) in Dedham, MA. The existing 4-span steel beam structure, built in 1934, will be replaced with a single span bridge. The proposed cross section will consist of two 12-foot travel lanes, a 12-foot paved shoulder, and a 6.5-foot sidewalk in both directions. An 18-foot wide raised median will separate each travel direction. Traffic will be maintained during construction, as the bridge will be replaced in stages.
Location:
  • Town of Dedham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2015
    Project Manager: Matt Hopkinson
    Estimated Construction Cost: $11,177,880.00
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 37067 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State an/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 05/11/2006
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 05/10/2006
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 06/08/2006
    Consultant Contract Process Workhours Approved 07/28/2008
    Consultant Contract Process NTP Issued 08/28/2008
    Design
    Right of Way
    Traffic
    Design Exceptions