Project Description:
DOVER- NEEDHAM- BRIDGE REPLACEMENT, D-10-005=N-04-006, CHESTNUT STREET OVER THE CHARLES RIVER
This bridge was originally constructed in 1922 and reconstructed in 1977. It is now considered structurally deficient and a design to replace the bridge has recently been initiated. Details of the replacement bridge type and number of spans have not yet been identified.
Location:
  • Town of Dover
  • Town of Needham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2015
    Project Manager: Shahpar Negah
    Estimated Construction Cost: $5,671,000.00
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 37073 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 05/17/2006
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 05/16/2006
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 06/26/2006
    Consultant Contract Process NTP Issued 09/07/2006
    Design
    Right of Way
    Requirements Requirements 10/08/2008
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating