| Project Description: |
CAMBRIDGE- INTERSECTION IMPROVEMENTS AT 7 INTERSECTIONS ON ROUTE 28 (MONSIGNOR O'BRIEN HIGHWAY)
Intersection improvements are needed to accommodate the relocation of the MBTA's Lechmere Station to the north side of O'Brien Highway. These improvements will provide improve pedestrian & bicycle access across O'Brien Highway to the new station and reduce congestion and queuing along O'Brien Highway.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Other |
| Project Manager: | Gautam Sen![]() |
| Estimated Construction Cost: | $11,120,000.00 |
| MassHighway District: | District 4 |
| Current Status: | Comments on the 25% design phase project plans have been returned to the Design Engineer. (as of 02/12/2007) |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||