Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HARWICH- INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 124 AND QUEEN ANNE ROAD
The project involves transportation improvements to the Queen Anne Road and Route 124 intersection located just south of the Route 6 (Mid-Cape Highway) Interchange #10. The poor level of service warrants the installation of a fully actuated traffic signal control system. Left turn lanes are proposed on both Route 124 approaches to improve overall operational characteristics. Other improvements include the following: expansion of the existing highway drainage system; revisions to travel lanes on the Route 124 southbound approach; truck turning movement improvements at the corners of the intersection; and pavement improvements with combined box widening and pavement overlays.
Location:
  • Town of Harwich
  • Construction Begins: Winter 2008/2009
    Construction Ends: Autumn 2010
    Resident Engineer: Joseph Gedraitis
    Construction Contract Value: $876,268.13
    Construction Bid Price: $759,842.05
    Initial Construction Estimate: $831,205.00
    MassHighway District: District 5

    Contracts (1) Progress
    # 57007 -- Construction Contract
    Harwich - Roadway Reconstruction and Related work at Intersection of Route 124 (Plasant Lake Avenue) and Queen Anne Road 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/02/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 11/29/2006
    Project Review Committee PRC Approved 12/14/2006
    Project Review Committee Letter 01/03/2007
    Project Status Initiated 11/28/2006
    Project Status Advertised 08/02/2008
    Prj Scope & Negotiation
    Design
    25% Design 25% Plans Received 03/19/2007
    25% Design 25% Comments to DE 09/07/2007
    25% Design Design Public Hearing 11/08/2007
    75% Design 75% Plans Received 02/21/2008
    75% Design 75% Comments to DE 05/02/2008
    100% Design 100% Plans Received 06/23/2008
    100% Design 100% Comments to DE 07/15/2008
    Final Design PS&E to FAPO 07/29/2008
    Final Design PS&E Received 07/25/2008
    Right of Way
    Certification Issued 07/01/2008
    Requirements Requirements 09/27/2007
    Requirements Requirements 05/08/2008
    Requirements Requirements 06/05/2008
    Traffic
    25% Design Review 25% Plans Received 05/02/2007
    25% Design Review 25% Plans Approved 07/16/2007
    75% Traffic Plans 75% Plans Received 03/03/2008
    75% Traffic Plans 75% Plans Approved 04/07/2008
    75% Draft Temp Signal 75% Plans Received 03/03/2008
    75% Draft Temp Signal 75% Plans Approved 04/07/2008
    100% Traffic Plans 100% Plans Received 06/23/2008
    100% Traffic Plans 100% Plans Approved 07/02/2008
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating