| Project Description: |
SOMERVILLE- STREETSCAPE IMPROVEMENTS ON BROADWAY
The project will reconstruct Broadway from Garfield Avenue to the Boston City Line. The roadway will be narrowed from four lanes to two lanes with marked bike lanes. The work includes wider sidewalks, pedestrian scale lighting, improved crosswalks with bump outs, bus stops and roadway realignment to create pedestrian activity nodes. Other amenities include bike racks, benches and landscaping.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Construction Begins: | Winter 2010/2011 |
| Project Manager: | Jocelyn Dewire![]() |
| Estimated Construction Cost: | $3,086,190.00 |
| Funding Provision: | This project is planned to be funded through the 2010 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
| MassHighway District: | District 4 |
| Current Status: | 75% Project Plans have been received. (as of 05/06/2010) |
|
Bridges |
||||||
|
|
|||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||