Project Description:
WOBURN- READING- STONEHAM-WAKEFIELD- INTERCHANGE IMPROVEMENTS TO I-93/I-95
MassDOT has begun development of Interchange Improvements to I-93/I-95 in Woburn, Reading, Stoneham, and Wakefield. The project area generally includes: Interstate 93 from Montvale Ave. (Exit 36) to Anderson RTC (exit 37C) and Interstate 95 between exits 36 and 41. More information is available at http://www.9395info.com/
Location:
  • Town of Reading
  • Town of Stoneham
  • Town of Wakefield
  • City of Woburn
  • Design Responsibility: Consultant
    Construction Begins: Winter 2021/2022
    Project Manager: Diane Madden
    Estimated Total Contract Cost: $266,088,970.80
    Estimated Total Federal Participating Construction Cost: $276,708,768.20
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (3) Progress
    # 57238 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as needed assignment basis over a period of 60 months. Final
    # 57738 -- Design -- Services
    Work will consist of preliminary and final design and the preparation of a Draft and Final EIR/EIS for improvements to the I-93/I-95 interchange. Final
    # 76798 -- Design -- MEPA/NEPA Compliance
    Modeling Support for I-93/I-95 Interchange EIS/EIR Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2009
    Project Initiation Form PIF Entered 07/28/2011
    Project Initiation Form PRC Submitted 05/07/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 05/14/2009
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating