Project Description:
CAMBRIDGE- IMPROVEMENTS AT ROUTE 2 & ROUTE 16
The purpose of this project is to perform minor widening, eliminating a merge condition, and improving throughput capacity and vehicle queue storage at the intersection of Route 2 and Route 16 (Alewide Brook Parkway).
Location:
  • City of Cambridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassHighway
    Construction Begins: Spring 2011
    Project Manager: Tracy Wu
    Estimated Construction Cost: $1,908,010.00
    MassHighway District: District 4
    Current Status: 25% Project Plans have been received. (as of 03/08/2010)

    Contracts (1) Progress
    # 57736 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2009
    Project Initiation Form PIF Entered 04/22/2009
    Project Initiation Form PIF Entered 04/22/2009
    Project Initiation Form PRC Submitted 04/22/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/05/2009
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 03/08/2010
    Right of Way
    Requirements Requirements 05/19/2010
    Traffic
    25% Design Review 25% Plans Received 03/10/2010
    25% Design Review 25% Plans Approved 03/30/2010
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating