DOVER- NEEDHAM- BRIDGE PRESERVATION, D-10-003=N-04-008, CENTRE STREET/CENTRAL AVENUE OVER THE CHARLES RIVER
The existing functionally obsolete bridge carrying Centre Street/Central Aveneu over the Charles River is to be widened to accommodate to two lanes of travel with two shoulders and possibly a sidewalk along the east side of the bridge. The widening of the roadway will consist of either widening both sides of the bridge by casting a structural slab and cantilevering the slab or by widening the bridge to the west only to extend the existing arches.
Location:
  • Town of Dover
  • Town of Needham
  • Right of Way Responsibility: Municipality
    Construction Begins: Winter 2013/2014
    Project Manager: Hemendra Bhatt
    Estimated Construction Cost: $1,884,200.00
    MassHighway District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/28/2009
    Project Initiation Form PIF Entered 05/07/2009
    Project Initiation Form PRC Submitted 05/07/2009
    Project Review Committee PRC Approved 05/14/2009
    Prj Scope & Negotiation
    Design
    Right of Way
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating