Project Description:
CANTON- IMPROVEMENTS ON ROUTE 138 (TURNPIKE STREET) FROM RANDOLPH STREET TO WASHINGTON STREET
The work for this project consists of roadway and sidewalk improvements on Route 138 between Randolph Street to Washington Street.
Location:
  • Town of Canton
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassHighway
    Construction Begins: Autumn 2010
    Project Manager: Albert Miller
    Estimated Construction Cost: $1,447,820.00
    Funding Provision: This project is planned to be funded through the 2010 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    MassHighway District: District 4
    Current Status: Final Plans, Specifications and Estimate have been forwarded to the Capital Expenditure Program Office (as of 07/30/2010)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2010
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CANTON
    Category: Advertised Projects Constr.
    Budget Section: 1
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category American Recovery & Reinvestment Act
    Federal Cost: $1,230,430.00
    State Cost: $0.00
    Total Cost: $1,230,430.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/24/2009
    Project Initiation Form PIF Entered 08/24/2009
    Project Initiation Form PRC Submitted 08/24/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Prj Scope & Negotiation
    Design
    Highway Design Process Design Public Hearing 03/15/2010
    100% Design 100% Plans Received 11/23/2009
    100% Design 100% Comments to DE 03/12/2010
    Final Design PS&E to CEPO 07/30/2010
    Final Design PS&E Received 07/23/2010
    Right of Way
    Certification Issued 07/26/2010
    Plans Accepted 04/15/2010
    Requirements Requirements 12/29/2009
    Advanced Title Exam Requested 02/12/2010
    Advanced Title Exam Completed 06/10/2010
    Registry Plans/Instruments Requested 04/15/2010
    Registry Plans/Instruments Accepted 07/08/2010
    Traffic
    100% Traffic Plans 100% Plans Received 12/18/2009
    100% Traffic Plans 100% Plans Approved 01/06/2010
    Design Exceptions
    Environmental
    Wetlands Protection Act Permit Issued 08/20/2008
    Wetlands Protection Act Permit Expires 08/20/2011
    ITS
    Utilities
    Non Participating