Project Description:
CANTON- SAFE ROUTES TO SCHOOL (HANSEN SCHOOL)
The project includes reconstructing and widening existing sidewalks on Pecunit Street and Kenney Street, installing new sidewalk on Pecunit Street near Charles Drive, reconfiguring the existing school parking lot on Pecunit Street, installing wheel chair ramps, crosswalks and installing a flashing pedestrian warning assembly on Washington Street.
Location:
  • Town of Canton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2010/2011
    Project Manager: Azad Kidher
    Estimated Construction Cost: $550,900.00
    MassHighway District: District 4
    Current Status: 75% Project Plans have been received. (as of 05/18/2010)

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/15/2009
    Project Initiation Form PIF Entered 10/15/2009
    Project Initiation Form PRC Submitted 10/19/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 05/18/2010
    75% Design 75% Plans Received 05/18/2010
    Right of Way
    Requirements Requirements 02/24/2010
    Traffic
    25% Design Review 25% Plans Received 05/19/2010
    25% Design Review 25% Plans Approved 06/21/2010
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating