Project Description:
BOSTON- DECK REPLACEMENT, B-16-056, CAMBRIDGE STREET OVER I-90, INCLUDES PRESERVATION OF B-16-057, LINCOLN STREET PED OVERPASS OVER I-90
Work consists of deck replacement of Cambridge Street over I-90 as well as preservation of Lincoln Street Pedestrian Overpass over I-90.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2014
    Project Manager: Manhar Patel
    Estimated Total Contract Cost: $11,525,733.55
    Estimated Total Federal Participating Construction Cost: N/A
    MassHighway District: District 6
    Current Status: This project has been advertised for construction bids. (as of 02/08/2014)

    Contracts (2) Progress
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/06/2010
    Project Initiation Form PIF Entered 01/21/2011
    Project Initiation Form PRC Submitted 01/21/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 02/08/2014
    Prj Scope & Negotiation
    Design
    Highway Design Process Design Public Hearing 06/18/2013
    Final Design PS&E to FAPO 02/04/2014
    Final Design PS&E to FAPO 04/22/2014
    Final Design PS&E Received 02/03/2014
    Final Design PS&E Received 04/22/2014
    100% Design 100% Plans Received 05/18/2012
    100% Design 100% Comments to DE 07/27/2012
    Right of Way
    Plans Requested 05/17/2012
    Plans Received 12/24/2012
    Plans Received 02/13/2013
    Plans Received 11/01/2013
    Plans Comments to DE 01/22/2013
    Plans Comments to DE 10/31/2013
    Plans Accepted 11/04/2013
    Requirements Requirements 05/17/2012
    Requirements Requirements 11/20/2013
    Advanced Title Exam Requested 02/14/2013
    Registry Plans/Instruments Requested 11/04/2013
    Traffic
    Design Exceptions
    Environmental
    ITS
    Utilities
    Non Participating