Project Description:
This project consists of reconstructing Beacon Street from the Cambridge city line to Oxford Street, an estimated distance of 1.1 miles. New sidewalks, curbing, drainage and signal improvements are included in the project.
  • City of Cambridge
  • City of Somerville
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Shawn Holland
    Estimated Total Contract Cost: $9,088,932.79
    Estimated Total Federal Participating Construction Cost: $2,785,830.54
    MassHighway District: District 4
    Current Status: This project has been advertised for construction bids. (as of 08/08/2015)

    Contracts (1) Progress
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final


  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    MassDOT is receiving a number of e-mail, telephone and feedback inquiry comments in support and in opposition to the project. Comments have been forwarded to appropriate MassDOT Individuals and Sections, as well as to the City who is the project proponent and designer of this local roadway project
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/19/2012
    Project Initiation Form PIF Entered 04/19/2012
    Project Initiation Form PRC Submitted 04/19/2012
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 08/08/2015
    Prj Scope & Negotiation
    Highway Design Process 25% Plans Received 04/24/2012
    Highway Design Process 25% Plans Received 05/01/2013
    Highway Design Process 25% Comments to DE 10/29/2012
    Highway Design Process 25% Comments to DE 07/01/2013
    Highway Design Process Design Public Hearing 02/04/2013
    75% Design 75% Plans Received 02/19/2014
    75% Design 75% Comments to DE 04/04/2014
    Final Design PS&E to FAPO 08/05/2015
    Final Design PS&E Received 09/05/2014
    Subsurface Exploration 100% Plans Received 06/16/2014
    Subsurface Exploration 100% Comments to DE 07/29/2014
    Right of Way
    Certification - Municipality Issued - All necessary ROW acquired 08/03/2015
    Plans Requested 03/12/2014
    Plans Received 02/19/2014
    Plans Received 09/08/2014
    Plans Reviewed 04/17/2012
    Plans Revised 10/04/2012
    Plans Revised 05/09/2013
    Plans Revised 03/12/2014
    Plans Revised 05/13/2014
    Design Exceptions
    Section Cleared 25% Plans Received 05/07/2012
    Non Participating