Project Description:
DEDHAM- BRIDGE REPLACEMENTS, D-05-029, PROVIDENCE HWY OVER HIGH & HARRIS STS & D-05-030, PROVIDENCE HWY OVER HARRIS ST.
This project will result in the replacement of the Providence Highway (formerly Route 1) bridge over High Street and the Providence Highway over Harris Street bridge with one bridge over both streets. The construction will be staged to maintain two lanes northbound and one lane southbound at all times. Reconstruction of the High Street/East Street intersection is also included.
Location:
  • Town of Dedham
  • Construction Begins: Spring 2005
    Construction Ends: Spring 2010
    Resident Engineer: Eric Zilinsky
    Construction Contract Value: $16,668,302.93
    Construction Bid Price: $14,315,649.35
    Initial Construction Estimate: $13,522,198.00
    MassHighway District: District 4

    Contracts (3) Progress
    # 39716 -- Construction Contract
    Dedham - Bridge Replacement D-05-029 (Concrete) - Providence Highway over High Street and Harris Street 99% Complete
    # 54136 -- Design -- Hwy Eng Open End
    Work will consist of provide engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 94010 -- Design -- Bridge Rehab/Recon/New Const
    DEDHAM-ROUTE 1 OVER ROUTE 135 Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/21/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Bridge Repl/Rehab
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 08/07/2004
    Project Status Advertised 12/18/2004
    Prj Scope & Negotiation
    Design
    Highway Design Process 25% Plans Received 02/12/1998
    Highway Design Process 25% Comments to DE 05/14/1998
    75% Design 75% Plans Received 02/13/2001
    75% Design 75% Plans Approved 10/22/2001
    75% Design 75% Comments to DE 10/22/2001
    25% 100% Plans Received 09/30/2003
    25% 100% Comments to DE 02/20/2004
    Final Design PS&E to CEPO 09/08/2003
    Final Design PS&E Received 09/08/2003
    Right of Way
    Traffic
    100% Temp Signal 100% Plans Approved 05/11/2004
    Design Exceptions
    Regular Design Exception Approved 11/08/2000
    Environmental
    ITS
    Utilities
    Non Participating