Project Description:
CHICOPEE- HOLYOKE- BRIDGE REHABILITATION, C-13-012=H-21-030, ROUTE 116 (CHICOPEE/CABOT ST) OVER CONNECTICUT RIVER & PV RR (AKA WILLIMANSETT BRIDGE)
The purpose of this project is to rehabilitate the existing bridge through the replacement of the bridge deck, sidewalks, and historic metal bridge railings. The existing bridge support structure will be repaired and strengthened and all structural steel will be repainted. A detour will be required during construction. The highway work will be limited to approach roadway work.
Location:
  • City of Chicopee
  • City of Holyoke
  • Construction Begins: Spring 2011
    Construction Ends: Autumn 2015
    Resident Engineer: Joseph Gaudet, Jr.
    Construction Contract Value: $13,357,446.00
    Construction Bid Price: $19,257,704.00
    Initial Construction Estimate: $28,674,663.75
    MassHighway District: District 2

    Contracts (11) Progress
    # 32104 -- Design -- Bridge Rehab/Recon/New Const
    Rehabilitation of Willimansett Bridge carrying Route 116 over the Connecticut River and Pioneer Valley Railroad in the cities of Chicopee and Holyoke. Final
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54833 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 55545 -- Design -- Bridge Open End
    Work will consist of reviewing Bridge Project estimates and preparing guidance for estimating of Bridge projects. Final
    # 57598 -- Design -- Hwy Eng Open End
    Work will consist of providing design and engineering services to MassHighway on a task order basis for various statewide Value Engineering Studies. Final
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68202 -- Construction Contract
    Willimansett Bridge Deck Replacement and Related Work (Including Painting) (C-13-012-=H21-030) (Steel) Route 116 (Cabot Street) over the Connecticut River and the Pioneer Va 100% Complete
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 94009 -- Design -- Highway
    CHICOPEE-HOLYOKE CABOT STREET Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BR REPLACEMENT
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/18/2010
    Prj Scope & Negotiation
    Consultant Contract Process Scope to DE 05/20/2002
    Consultant Contract Process Workhours Approved 12/16/2003
    Consultant Contract Process NTP Issued 05/21/2004
    Design
    Type Study 25% Plans Received 12/11/2007
    Type Study 25% Comments to DE 06/19/2007
    Type Study Design Public Hearing 04/16/2009
    75% Design 75% Plans Received 11/10/2009
    75% Design 75% Comments to DE 12/18/2009
    Distribution of Plans 100% Plans Received 04/14/2010
    Final Design PS&E Received 08/24/2010
    Right of Way
    Certification Issued 09/15/2010
    Plans Received 07/15/2010
    Plans Comments to DE 07/30/2010
    Plans Accepted 07/30/2010
    Requirements Requirements 07/15/2010
    Advanced Title Exam Requested 02/28/2010
    Advanced Title Exam Completed 02/19/2010
    Registry Plans/Instruments Received 08/24/2010
    Registry Plans/Instruments Comments to DE 09/13/2010
    Traffic
    25% Design Review 25% Plans Received 10/04/2005
    25% Design Review 25% Plans Approved 01/05/2006
    75% Traffic Plans 75% Plans Received 11/17/2009
    75% Traffic Plans 75% Plans Approved 12/15/2009
    Design Exceptions
    Environmental
    Section 401 (WQC) Permit Issued 07/12/2010
    Section 401 (WQC) Permit Expires 07/14/2015
    ITS
    Utilities
    Non Participating