Project Description:
DANVERS- RECONSTRUCTION OF TWO INTERCHANGES ON ROUTE 128, WITH ROUTE 62 AND ROUTE 128 WITH ROUTE 35, INCLUDES REPLACEMENT OF D-03-020 (PHASE I)
This purpose of this project is to construct new acceleration/deceleration lanes at the Route 35 (High Street) and Route 62 (Elliot Street) interchanges. The project also proposed to replace the bridge carrying Route 128 over an unused MBTA rail road located south of the High Street interchange.
Location:
  • Town of Danvers
  • Construction Begins: Winter 2009/2010
    Construction Ends: Autumn 2012
    Resident Engineer: Susan Cranney
    Construction Contract Value: $27,591,539.44
    Construction Bid Price: $20,147,249.16
    Initial Construction Estimate: $27,183,217.00
    MassHighway District: District 4

    Contracts (5) Progress
    # 34692 -- Design -- Hwy Eng Open End
    Statewide - provide engineering design and review services to the Projects Division on an open end basis for various statewide highway and bridge projects. Final
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57731 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60072 -- Construction Contract
    Roadway Reconstruction on a Section of Route 128 Including Replacement of Bridge (D-03-020) (Steel). 100% Complete
    # 97467 -- Design -- Highway
    DANVERS- PEABODY- ROADWAY IMPROVEMENTS ON ROUTE 128 FROM ROUTE 62 DANVERS SOUTH TO SHOPPING CENTER BRIDGE PEABODY (ROUTE 114) Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/04/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Received 02/12/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 07/25/2009
    Prj Scope & Negotiation
    Consultant Contract Process Workhours Approved 08/22/1997
    Consultant Contract Process NTP Issued 12/20/2000
    Design
    Highway Design Process 25% Plans Received 01/02/2002
    Highway Design Process Design Public Hearing 06/24/2004
    75% Design 75% Plans Received 01/07/2005
    75% Design 75% Comments to DE 06/26/2006
    Final Design PS&E to FAPO 07/09/2009
    Final Design PS&E Received 07/06/2009
    Subsurface Exploration 100% Plans Received 02/09/2007
    Subsurface Exploration 100% Comments to DE 09/17/2007
    Right of Way
    Certification - MassDOT Issued - All necessary ROW acquired 07/08/2009
    Plans Received 02/27/2012
    Plans Comments to DE 02/22/2012
    Plans Comments to DE 07/26/2012
    Plans Accepted 03/01/2012
    Requirements Requirements 01/15/2009
    Advanced Title Exam Requested 07/15/2005
    Advanced Title Exam Completed 06/18/2008
    Registry Plans/Instruments Requested 03/21/2012
    Registry Plans/Instruments Accepted 05/21/2009
    Traffic
    75% Design Review 75% Plans Received 01/07/2005
    75% Design Review 75% Plans Approved 03/02/2005
    75% Traffic Plans 75% Plans Received 01/07/2005
    75% Traffic Plans 75% Plans Approved 03/02/2005
    75% Draft Temp Signal 75% Plans Received 01/07/2005
    75% Draft Temp Signal 75% Plans Approved 03/02/2005
    75% TMP 75% Plans Received 01/07/2005
    75% TMP 75% Plans Approved 03/02/2005
    75% TCA 75% Plans Approved 01/07/2005
    75% TCA 75% Plans Received 01/07/2005
    100% Design Review 100% Plans Received 01/11/2007
    100% Design Review 100% Plans Approved 06/05/2007
    100% Traffic Plans 100% Plans Received 03/12/2009
    100% Traffic Plans 100% Plans Approved 06/02/2009
    100% Temp Signal 100% Plans Received 01/11/2007
    100% Temp Signal 100% Plans Approved 06/04/2007
    100% TCA 100% Plans Received 01/11/2007
    Design Exceptions
    Regular Design Exception Approved 09/09/2003
    Environmental
    Wetlands Protection Act Permit Issued 08/04/2008
    Wetlands Protection Act Permit Expires 08/04/2011
    ITS
    Utilities
    Non Participating